Attendance for construction
Attendance is the main contractor’s mark up for specific services it has to provide for individual suppliers or sub-contractors. This might include items such as material handling, scaffolding and rubbish clearance.
Attendance can be ‘general’ or ‘special’.
General attendance is the description of main contractor attendance available site wide to all suppliers or sub-contractors such as:
- Welfare facilities.
- External scaffolding.
- Temporary power and lighting.
- Platform and passenger hoists.
- Tower crane lifts by prior arrangement.
- Site security.
- Waste disposal.
Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor, such as:
- Special hoists.
- Builders work such as a concrete plinth.
- Special scaffolding.
It is important to establish within the contract documents whether items that suppliers or sub-contractors require will constitute attendances that will be provided by the main contractor, or whether they will provide them themselves (such as their own specialist equipment).
Attendance should not be confused with general site preliminaries or builder’s work in connection with mechanical and electrical services. These items are separately priced.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.